Get the free template
What's in the workbook (4)
Every tab starts with real content from our guides, so you are editing, not starting from a blank sheet. A "Start here" tab explains how to use it.
- 01
Plan
Twenty-six tasks across discovery, design, build, testing, launch and hypercare; dates calculate from your start date and a 16-week timeline shades itself.
Columns: Phase · Task · Owner · Start week · End week · Start date · End date · Status · Notes · W1 to W16. You enter the project start date once at the top; Status offers Not started, In progress, Blocked and Done, with Blocked and Done highlighted.
- 02
Responsibilities
A responsibility chart for eleven deliverables across eight roles, so every deliverable has one accountable person.
Columns: Deliverables from scope and priorities to post-launch support, against executive sponsor, project owner, business process owners, Salesforce admin, data owner, IT and security, partner project lead and partner consultants. Each cell takes R, A, C, I or A/R.
- 03
Risks
A risk log with five common Salesforce project risks and their mitigations to start from.
Columns: ID · Risk · Likelihood · Impact · Mitigation · Owner · Status. Thirty numbered rows; likelihood and impact take Low, Medium or High, and status takes Open, Mitigating or Closed.
- 04
Decisions
A decision log with the options considered and the impact on scope or timeline.
Columns: Date · Decision · Options considered · Decided by · Impact on scope or timeline. Forty rows, so the reasons behind the build survive the project team.
Who uses it, and when (4)
Start it at kickoff, or the day the scope is signed, and keep it on your side of the project even if your partner runs their own delivery plan. The example tasks follow a 12-week Sales and Service Cloud project, with roughly 15% of the time in discovery, 15% in design, 35% in build, 15% in testing, 10% in launch and 10% in hypercare. Those are the workbook’s example proportions, not a promise about your project: the timeline runs to week 16 so you can stretch it without rebuilding the sheet.
Who works in it
- Project owner keeps owners and status current and runs the weekly review from the Plan tab.
- Executive sponsor reads the timeline, the open risks and the decision log, and holds the go/no-go call.
- Partner project lead lines up their delivery plan with your weeks and flags slippage early.
- Salesforce admin inherits the decision log at handover, so they know why the org was built the way it was.
How to use it, step by step (6)
- 01
Enter the start date
Type your kickoff date at the top of the Plan tab. If it is a Monday, every task starts on a Monday and ends on the Friday of its last week, because the end date is calculated three days short of the full week.
- 02
Fit the weeks to your scope
Change Start week and End week for each task. The dates and the shaded timeline redraw on their own, so you can try a longer build or an extra testing week and see the knock-on effect straight away.
- 03
Put a person in every Owner cell
A team name is not an owner. If nobody will take a task, that is the first risk to log.
- 04
Fill in the responsibility chart in week one
Give each deliverable exactly one A. Use A/R where the accountable person also does the work.
- 05
Review it every week
Update status, read every Blocked row out loud, add new risks and write down each decision with who made it and what it changed.
- 06
Protect testing and hypercare
If build runs late, move the launch rather than shrinking user acceptance testing to a few days. The workbook’s own guidance is that squeezed testing moves defects into production.
Mistakes it helps you avoid (5)
Late build quietly eating testing time
Because the testing and launch rows have their own weeks, a slip in build shows up as an overlap you have to resolve on purpose.
Decisions that wait
The first seeded risk is decision-makers being unavailable. A dated decision log shows exactly where waiting cost time.
Two people accountable for one thing
The chart’s rule is one A per deliverable, which matters most for requirements sign-off and the go/no-go decision.
Treating hypercare as optional
Three hypercare tasks, including adoption tracking by team and a handover backlog for phase two, keep the weeks after launch on the plan.
Testers who were never booked
Another seeded risk: freeing testers from their day jobs has to be arranged at kickoff, not the week UAT starts.
How it works with the other templates (3)
- Salesforce RFP and Partner Scoring Workbook: Its Proposal comparison rows for discovery, hypercare and assumptions about your team’s time are what you check this plan against once a partner is chosen.
- Salesforce Data Migration Workbook: The plan’s data inventory, mapping approval, test load, rehearsal and final load tasks are each run from a tab in the migration workbook; take their status from there.
- Salesforce UAT Test Script Workbook: The test script, UAT and go/no-go tasks are run with the UAT workbook, and its Sign-off tab is the written evidence behind the go/no-go row.
Related pages
- Implementation readiness assessment: a free check of whether your team is ready to start week one.
- Salesforce go-live checklist: the detail behind the launch-phase rows.
- Salesforce training plan: how to run the training-by-role task well.
- Salesforce project rescue: if the plan already shows a project that is badly off track.
Questions about the implementation project plan (5)
Why does the timeline run to 16 weeks when the example is 12?
So the plan can absorb what discovery uncovers. If you find another integration or a messier data source, push the end weeks out and the shading follows, without adding columns or rewriting formulas.
How are the task dates calculated?
The start date is the project start plus seven days for every week before the task’s start week. The end date is the project start plus seven days for each week up to the end week, minus three days. With a Monday start date that gives a Monday start and a Friday finish for every task.
Can we use it for a phased rollout?
Yes. The example notes that larger programs repeat build, test and launch for each release. Copy the build, testing and launch rows for each release and give them later weeks, or keep a copy of the Plan tab per release.
What is the difference between R and A on the Responsibilities tab?
R is the person who does the work. A is the one person who makes the call and answers for the result. Several people can be R or C on a deliverable, but only one can be A. Use A/R when one person is both.
We already have our partner’s project plan. Do we need this as well?
Usually, yes. A partner’s plan tracks the partner’s tasks. This one tracks the work only your side can do, such as decisions, data ownership, tester time and sign-offs, which is where projects most often wait.
The guidance behind it (2)
This template follows the advice in our guides, written by the consultants at Abstrakt Solutions, a Salesforce Select partner with 138 certifications.